First Article Inspection

Steps of a First Article Inspection

1. CEI will do a detailed analysis of the customer’s component print and will balloon and number all dimensions and specifications.

first article 01 First Article Inspection

2. CEI will complete a full inspection of the part and complete the first article inspection form.

first article 02 First Article Inspection

3. CEI is able to document a manufacturing process a number of ways. One of them is a process flowchart.

first article 03 First Article Inspection
Another is a supplier control plan.

first article 04 First Article Inspection
4. When required, CEI can also include a process Potential Failure and Effects Analysis (PFEA).

first article 05 First Article Inspection
Also when required, CEI can produce Gage R&R’s and Statistical Capability Studies.

first article 06 First Article Inspection

first article 07 First Article Inspection
5. If there are specific formats that are essential, CEI can always accommodate the additional requirements of our customers.

All of the above documentation, along with any additional documents specifically required by the customer, may be incorporated into a PPAP (Production Part Approval Process) submission, under AIAG (Automotive Industry Action Group) guidelines.

part submission warrant 1 First Article Inspection

You may also be interested in:

  1. About Us
  2. Quality Assurance Department
  3. Metal Stamping

All manufacturing takes place in the United States at our facility in Wallingford, CT. Component Engineers Inc. offers a variety of contract manufacturing services. Please see other custom services offered by CEI. We are an ISO registered custom manufacturer in business since 1980.